Test Fluid Supply for Pipeline Fill

The Challenge

A client required test fluid to fill a pipeline efficiently. With a massive volume to move, the job required high-capacity trucks, precise control, and zero delays. Any miscalculation in flow rate or supply coordination could cause inefficiencies, extend the project timeline, or create operational issues.

The XACT Solution

XACT Pressure Services brought in a tri-drive pressure truck capable of pumping at 1.2m³ per minute, ensuring the pipeline was filled quickly and efficiently. Our team:

  • Supplied and managed the entire 5,575m³ test fluid fill, preventing downtime and shortages.

  • Utilized our high-capacity pressure truck to maintain a steady, controlled flow rate.

  • Monitored the process in real time to ensure smooth operations and accurate volume delivery.

  • Kept communication lines open to coordinate with on-site crews and adapt to any changes.

The Result

With XACT Pressure Services’ experience and powerful tri-drive pressure truck, the pipeline fill was completed on time and without disruption. Our team allowed the client could focus on their operations without worrying about fluid supply or pumping inefficiencies.